IRT Conducts In-Situ Chemical Oxidation Program at an Active Filling Station

IRT recently completed an injection program at an active gasoline filling station/convenience center located in the Midwest. The project included on-site mixing and injection of 4,900 gallons of our patented formulation to remediate a historical gasoline release. The injected formulation will continue to generate oxygen in the subsurface and the included nutrients will enhance the bioremediation process for up to one year or more. IRT completed this work with no business interruption to the site occupant whereas conventional remediation would have resulted in significant loss of business.